Local Law 97 enforcement has started. Here is the process DOB describes for over-limit and non-filing condo and co-op boards.
DOB's report on calendar 2024 counts 470 Article 320 properties over their limits and 599 that did not file. Its process starts with a Notice of Deficiency, not a court filing, and the clock runs from the notice date. Read the notice and talk to counsel about your dates. Related: LL97 overview.
Local Law 97 set carbon emissions limits for large NYC buildings starting in calendar year 2024, generally those over 25,000 square feet. DOB's first-year report says about 95 percent of required properties filed. Of the Article 320 properties that filed, 95 percent met their limits. Those over their limits, and the 599 that did not file, are where enforcement now starts. DOB says it has issued Notices of Deficiency for failure to file and for buildings exceeding limits. DOB's enforcement presentation describes a Notice of Deficiency with a response window, and only after that a petition at the Office of Administrative Trials and Hearings. A board that does not know whether it has received a notice should find out now.
What the Department of Buildings reported.
The report covers calendar 2024 only. Of 19,963 properties required to report, representing 29,031 buildings, about 95 percent filed. Article 320, the annual-limits pathway that covers many market-rate condos and co-ops, accounts for 11,036 of those properties. Of those, 10,437 filed, 9,951 met their limits, 470 were above their limits, 16 filed with data-quality problems, and 599 did not file. Among those above their limits, 149 requested penalty mitigation for good faith efforts. DOB extended the first-year filing deadline to December 31, 2025.
Reports for calendar 2025 were due by May 1 and no later than June 30, 2026, with an extension available to August 29, 2026. The DOB documents we read do not report results for that year, so 2025 exposure depends on filings not yet summarized. DOB says it designed enforcement "to focus on achieving emissions reductions and preserving penalties for owners that do not engage or fail to follow through."
The penalties differ by violation. For Article 320, failure to report is up to floor area times $0.50 for each month within the 12 months following the deadline. Exceeding the limit is up to actual emissions minus the limit, times $268 per year, under §28-320.6. DOB's rule calculates the penalties at those full amounts. A building 200 metric tons over would face $53,600 for that year, and one 1,000 tons over would face $268,000. A 25,000-square-foot non-filer would face $12,500 per month, per DOB's example. Limits are set under §28-320.3.1 and vary with floor area and occupancy type. Article 321 buildings, many of them affordable housing, are different: a $10,000 penalty, processed through DOB violations on DOB NOW rather than at OATH.
What a Notice of Deficiency contains.
Per DOB's presentation, the notice identifies:
- The notice number and issuance date
- The owner
- The premises: borough-block-lot, building identification number and address
- The legal basis
- How the penalty is calculated
- The potential penalty amount
- Instructions for resolving the deficiency
- That no action within a set number of days of the notice date could escalate the matter to OATH for civil penalty recovery
The stated amount is a potential penalty. Terminology varies across DOB materials: the Article 320 guide's flowchart refers to a notice of violation and the rule refers to summonses. Rely on what your notice says.
The enforcement process, step by step.
- DOB issues the Notice of Deficiency. The response period runs from the notice date on the document, not from when it reaches the board.
- Over the limit: within 30 days of the notice date, the owner can correct by buying offsets to cover all or part of the deficiency, indicate payment through BEAM Ticket 17, or challenge the notice through BEAM Ticket 17. The code caps greenhouse gas offset deductions for 2024 through 2029 at 10 percent of the building's annual limit, so ask how much of your deficiency offsets can cover.
- Failure to file: within 60 days of the notice date, the owner can resolve with zero penalty by submitting an extension request and the annual report, indicate payment through Ticket 17, or challenge through Ticket 17.
- If the deficiency is not resolved, DOB serves a petition and the matter proceeds to trial at OATH.
- OATH's rules say the respondent may answer within eight days of personal service or thirteen days of service by mail, unless the judge sets a different time. The judge may require an answer, and failing to file one where required may bring sanctions. A notice of trial must warn that failure to appear may result in a default and a waiver of the right to a trial.
- DOB's flowchart says "Penalty will be assessed on the building record post trial." Local Law 97 also allows penalties to be recovered in an action by the corporation counsel. DOB says some owners elect to pay and avoid the OATH proceeding.
Mitigation and Mediated Resolution.
1 RCNY 103-14(i) says mitigating factors "must be filed with the building emissions report." They include an unexpected or unforeseeable event, such as disaster damage, which may result in a penalty of zero dollars for that year, and good faith efforts. Good faith requires the previous year's emissions report, benchmarking and a lighting and sub-meter attestation, plus at least one further showing. One showing is a decarbonization plan, which the rule dates no later than May 1, 2025, and which then carries its own later requirements. DOB's February 2026 timeline slide appears to show the first report and plan due December 31, 2025, after the first-year extension, so check the date that applied to you. DOB's presentation lists others, including work underway, electrification readiness, previous compliance and a financing adjustment. So a board that missed the plan date should not assume mitigation is closed for later years. Because claims go in with the report, ask early what can still be raised for a year already filed.
DOB also describes Mediated Resolution: a formal agreement between owner and department. Its presentation says one may be offered when mitigation criteria are not fully met or additional steps or ongoing oversight are needed. The penalty is "waived, in whole or in part, contingent upon the owner's compliance with the terms of the agreement," and failing those terms may bring back penalties for previously waived years. The Article 320 guide says LL97 penalty amounts "are negotiated by the Department itself" when one is requested. The rule limits the offer to owners who filed a report and showed good faith efforts, including the listed criteria "or other demonstrated effort," where the resolution would help the building meet its limit. The guide says how to ask: an owner requests one by providing documentation of good faith efforts when submitting the building's annual emissions report, and the deadlines for applications are the same as those for that report. Only one approved resolution is required per compliance period, and each compliance timeline is building-specific. So the time to ask may come well before any notice. The guide does not say whether a request can still be made after a Notice of Deficiency, and it predates DOB's February 2026 presentation, so ask DOB and counsel immediately rather than assuming the notice window is open for this. DOB also says it is working with NYC Accelerator to support owners that show a credible path to compliance.
Who is watching the file.
The notice identifies the owner, and the owner bears the penalty. A board that relies on a managing agent to watch BEAM, open mail and gather energy data should confirm that someone is actually doing so, because the clock does not wait for the document to be forwarded.
We found no license specific to condo and co-op managing agents, so a board cannot rely on one to show that an agent knows emissions accounting or OATH procedure. S.71 would have required property managers with 25 or more residential units in their portfolio to register with the Secretary of State and be certified, with Attorney General enforcement. It did not pass in nine consecutive sessions, had no Assembly same-as, and its sponsor is leaving the Senate.
Until that changes, the board's protection is direct oversight. Ask your managing agent: Has a Notice of Deficiency been issued for any year? What is its notice date? What has been submitted through BEAM? Are offsets, payment, a challenge or a Mediated Resolution being considered? Has counsel seen it? Ask for the documents.
Bottom line.
DOB's process starts with a Notice of Deficiency: 30 days from the notice date if the building is over its limit, 60 if it failed to file. The options are in the notice and in DOB's enforcement materials. Unresolved matters go to OATH, which has its own much shorter window to answer once a petition is served (eight or thirteen days), and the judge may require an answer.
The board needs to know whether a notice exists, what date is on it, and what response has been filed. Read the notice itself, and ask counsel to confirm your deadlines, because this article is a summary of DOB's materials and not legal advice.
Correction: An earlier version of this article said boards had 30 days to answer at OATH, when DOB's process starts with a Notice of Deficiency; described an unsourced default surcharge, lien path and May 2026 Good Faith Effort deadline; misstated DOB's figures; and said DOB does not explain how to request a Mediated Resolution. The article was corrected on November 5, 2026.