The LL97 annual filing
grace period closes
June 30. Here is
the penalty math.
Reports missing after the 60-day window face $0.50 per square foot per month. Buildings over their limit are liable for $268 per metric ton of CO2-equivalent. Companion to our Local Law 97 overview.
Local Law 97 carries two separate financial penalties: one for failing to file the annual emissions report, and one for reporting emissions above the legal limit. They are calculated differently. June 30, 2026 is the end of the 60-day window for this year's report. A building over its limit for 2025 is liable for the second penalty whether or not it files on time. This post separates the two and shows the math on each. If you are reading after June 30, see the end of the section on what to do.
Two penalties.
The first is a late-filing penalty. Most buildings with Article 320 limits must file by May 1 of the year after the calendar year being reported. Under DOB's enforcement presentation, some start later: buildings with under 35% rent-regulated units report from 2027, and income-restricted buildings from 2036. Check the Covered Buildings List. DOB says "No penalties will be issued if the report is filed within 60 days of May 1." After that, 1 RCNY 103-14(g) sets the penalty as gross floor area multiplied by $0.50 "for each month such report is not submitted within the 12 months following May 1 of each year, including the 60 days following the deadline." A 25,000-square-foot building faces $12,500 per month at that rate. A 200,000-square-foot building faces $100,000 per month. DOB describes a way to cure a missed filing, covered below.
The second is an emissions penalty. A building over its limit is liable for $268 per metric ton of CO2-equivalent over the limit, per calendar year, under 103-14(h). Filing on time does not by itself reduce it. What can reduce it is covered below: actual cuts, offsets, and the rule's mitigation provisions.
What the June 30 deadline covers.
The report for 2025 energy use was due May 1, 2026. DOB's February 27 service notice says reports are due by May 1 and no later than June 30, 2026. If that window is missed, the rule counts months as quoted above, "including the 60 days following the deadline." DOB's documents do not spell out more, so ask DOB or counsel if your building is affected.
DOB's notice says owners also have until June 30 to apply to extend the reporting deadline to August 29, 2026; see its extension user guide. The NYC Accelerator describes the application as made through the NYC Building Energy Analysis Manager (BEAM) portal for a $60 fee, and DOB says payments for extensions must be submitted in DOB NOW: Safety. An extension moves the report date. It does not change a building's limit or reduce an emissions penalty.
The emissions penalty calculation.
Limits are set by 1 RCNY 103-14 by property type. For Multifamily Housing, the factor for the 2024-2029 period is 0.00675 tCO2e per square foot, or 6.75 kilograms. For calendar years 2030-2034, the rule's factor is 0.00334664, about 3.35 kilograms, roughly half. (The 2019 law's occupancy-group figure was 4.07 kilograms; the rule's option to use occupancy-group limits is stated for 2024 and 2025 reports only. Confirm your building's figure with your energy professional.)
A building's limit is the factor multiplied by gross floor area. Emissions above that are multiplied by $268.
| Building size | Actual rate (kgCO2e/sf) | Cap (6.75 × sf ÷ 1,000) | Excess (metric tons) | Annual penalty at $268/ton |
|---|---|---|---|---|
| 100,000 sf | 7.25 | 675 tCO2e | 50 | $13,400 |
| 150,000 sf | 7.50 | 1,012.5 tCO2e | 112.5 | $30,150 |
| 200,000 sf | 8.00 | 1,350 tCO2e | 250 | $67,000 |
These figures recur every year a building stays over its limit, at the same $268. Based on 2024 energy performance data, the Urban Green Council estimates that about 9 percent of properties exceed their 2024 cap. DOB's first-year report, completed after this article was first published, shows 470 Article 320 filings above the limit, 5% of filings.
Good faith efforts: one path has closed, others remain.
1 RCNY 103-14(i) says an owner over its limit "may be eligible for a mitigated penalty" for an unexpected or unforeseeable event or for demonstrated good faith efforts. Mitigating factors "must be filed with the building emissions report." Good faith requires filing the report and benchmarking, attesting to lighting and sub-meter compliance, and one or more of several other showings.
One of those, submitting a certified decarbonization plan, closed on May 1, 2025. Others remain in the rule: an approved application or contract for the work needed to meet the 2024-2029 limit, work underway toward electric readiness, a prior report under the limit in this compliance period, a critical-facility showing, or an application for an adjustment. A building without a plan is not out of options. Each has its own conditions, and a plan filer may not claim deductions for renewable energy credits, so read the rule. Mitigation is not automatic: the rule says these "may result in" a mitigated penalty.
The rule also lets DOB offer a mediated resolution to an owner that filed a report, has shown good faith efforts, and where the resolution would help the building meet its limit. And DOB's enforcement presentation lists purchasing offsets as a way to correct a Notice of Deficiency for going over the limit, "all or part of the deficiency." The NYC Accelerator describes the offset as priced at $268 per ton, the same as the penalty, and capped at 10% of the building's annual emissions limit, so it may not cover a large overage and costs as much per ton. These are DOB's descriptions; a Notice of Deficiency sets its own deadlines, so read it and talk to counsel.
A building 250 tons over faces $67,000 for 2025 at $268 a ton, and the same for each later year it stays 250 tons over. In 2030 the limit tightens, so the overage grows even if the building's emissions do not.
Which buildings face the most exposure.
The Urban Green Council says about 57 percent of properties currently emit more than their 2030 cap. A multifamily building emitting 6.5 kgCO2e/sf is just under the current 6.75 factor and would be about 94 percent above the rule's 3.35 factor for 2030. In our view the current period is the time to do the work, not only to study it.
The NYC Accelerator offers free help and says you can see a building's LL97 exposure on its Momentum platform.
What to do before June 30.
If the 2025 report has not been filed, two options remain before June 30:
- File through the BEAM portal by June 30. The Accelerator says reports are submitted with the help of a registered design professional. Ask your managing agent or energy consultant where yours stands.
- Apply for the extension by June 30. It moves the reporting deadline to August 29, 2026. It does not reduce any emissions penalty.
If those dates have passed: for a Notice of Deficiency for failure to file, DOB's February 2026 presentation lists "Resolve with zero penalty by submitting an extension request and the annual emissions report," with steps to be taken within 60 days of the Notice Date. That presentation predates this year's deadlines, so confirm with DOB that it applies to your notice. If the building is over its limit, retain an energy consultant, and ask counsel which mitigation paths in 103-14(i) fit, since those must be filed with the report.
Bottom line.
LL97 has two separate penalties. Filing by June 30, or getting an extension to August 29, addresses the first. The second is $268 per metric ton for every year a building is over its limit, and that rate does not change under the rule we read. The decarbonization-plan path closed May 1, 2025, but other good-faith paths remain, filed with the report. The multifamily factor for 2030-2034 is about half of today's. In our view, June 30 is one date and the larger exposure is the 2030 limit.
Correction: An earlier version of this article gave May 1, 2026 as the decarbonization-plan deadline (it was May 1, 2025) and said a building without one faced a $404-per-ton rate. The rule's rate is $268. It also said no reduction could be started after the fact, and used 4.07 kg as the 2030 multifamily limit rather than DOB's 3.35. The article was corrected on November 5, 2026.
Primary sources: 1 RCNY 103-14; DOB, Enforcement of Article 320 of LL97 (Feb. 2026); DOB service notice, Feb. 27, 2026; DOB, Local Law 97: 2024 Compliance and Reporting Rates; NYC Local Law 97 of 2019; NYC DOB LL97 Extension Request User Guide; NYC Accelerator, LL97; Urban Green Council LL97 analysis.
Companion resources: Local Law 97: The Retrofit Bill and the $268 Penalty • C-PACE financing gap for co-ops and condos • FDNY steam-era staffing rules and LL97 retrofit costs • NYC Electrical Code 2025 and LL97 retrofit permits • The NYC local law extraction stack